The Contingency Number Most Builders Won't Give You

Everyone says "budget a contingency." Nobody says how much. Here is the actual number, and the floor it should never drop below.

By Beckett Stone·October 11, 2026·3 min

The Short Answer

Start at 10% of the bid. On a $1M project that's $100,000. Narrow it as scopes lock, but never below $30,000 on any job. If less than 50% of the project is hard-bid with contractible sub offers, carry $150,000 on a $1M build and $150,000–$200,000 on a $2–3M build.

Ten percent. That's where it starts on every project. A million-dollar bid gets roughly a hundred thousand dollars of contingency sitting in reserve from day one. That number narrows fast as the bid sharpens and scopes get locked down. But it never goes below thirty thousand dollars. Not on any project. There is always thirty thousand dollars of unexpected cost, upgrade, or item you didn't see coming.

Start at 10%. Floor It at $30K.

Most builders say "ten to fifteen percent" and move on. That's not an answer, that's a shrug with a number attached. The useful part is what happens after the ten percent. As bids come in and real scopes get signed, the contingency should tighten. That's the whole point. A contingency that never moves means nobody is sharpening anything.

But it stops at thirty thousand. That's the floor. Below that you're not carrying a contingency, you're carrying a rounding error.

What It's Actually For

Contingency is for items that are not upgrades. Material cost influxes. A category that moved across the board because the market moved. That's the lane it's supposed to stay in.

What actually happens is different. A client gets to the countertop decision and says they want to go from quartz to quartzite. That's another ten thousand dollars. And if there's room, you squeeze it out of the contingency. It's not what the money was set aside for. It's what the money ends up doing.

The distinction matters because the order of operations matters. If contingency becomes an upgrade budget in month two, there's nothing left when the market moves in month eight.

If the Bid Isn't Hard, Carry More

Here's the test nobody runs. Look at the bid and ask how much of it is hard-bid with contractible offers from the subcontractors. If it's less than half, the rest is an estimate dressed up as a number.

In that case, the minimum is a hundred thousand dollars. On a million-dollar project, keep a hundred and fifty. On anything over a million — call it a two to three million dollar project — keep a hundred and fifty to two hundred thousand in there. Minimum. Not because anyone is incompetent. Because the numbers aren't locked and you need to have already processed and swallowed what the price could be.

That last part is the real work. The money matters less than the mental accounting. If you've already accepted that the number could be two-point-two, two-point-two doesn't break you.

The Bonus at the End

A builder who fights for savings for you changes the math on all of this. Beat a budget item here. Beat another one there. It compounds over the length of a job.

So on a two-million-dollar project, the two hundred thousand you carried and never spent isn't waste. It's the best possible ending. You underwrote the risk, the risk didn't show up, and you keep the money. That's an added bonus at the end of the project, not a planning failure.

“Have it in there. Be ready to spend it. Then it's just a bonus if you don't.”

— Beckett Stone

The Short Version

  • Start at 10% of the bid — $100,000 on a $1M project
  • Narrow it as scopes lock, but never below $30,000
  • Use it for material cost influxes and market movement, not upgrades
  • Expect upgrades to pull from it anyway — the quartz-to-quartzite swap is real
  • Less than 50% hard-bid with contractible sub offers? $100,000 minimum
  • $1M project: keep $150,000. $2M–$3M: keep $150,000–$200,000 minimum
  • Unspent contingency at the end is the win, not the waste

Planning a Custom Build and Want the Real Number?

If you're looking at a bid and trying to figure out what to carry behind it, let's talk through it.

Start a Project
Beckett Stone — Bijou Builds

About the Author

Beckett Stone

Build Advisor · Bijou Builds, Austin

Beckett writes about luxury remodels, custom homes, and the materials and techniques that separate a great Austin build from a forgettable one. He is also the AI advisor on every page at bijoubuilds.com. Same opinions in both places.

Start a Project →